Balmina Sehra
USAG Stuttgart Public Affairs
STUTTGART, Germany — Closed roads, detours and the occasional crane are becoming familiar sights around U.S. Army Garrison Stuttgart. Construction can slow commutes and test drivers’ patience, but the work is about more than short-term inconvenience.
Across the garrison, workers are repairing aging infrastructure, updating building systems and constructing new facilities to meet safety and security standards. The projects are part of a long-term effort to improve quality of life and keep the community safe.
“These projects are evidence of the garrison’s steps to bring the installation into the 21st century,” said Terry Walker, chief of the engineering division for the Directorate of Public Works.
Walker said the DPW is working closely with host-nation partners to keep projects on schedule and limit disruptions. “We are forging the future of USAG Stuttgart, ” said Jean Pierre Messier, deputy to the director of Public Works. “This transformation ensures that we will continue to stand as a preeminent platform, empowering our joint mission partners to succeed for decades to come.”
Here is a look at the construction projects shaping USAG Stuttgart in 2026 and what the community can expect.
Panzer Kaserne
New Commissary building next to Panzer Exchange
• Start: December 2024
• Cost: $51 million
• Work: Build a new, consolidated commissary, no impact to traffic flow on post.
• Estimated completion: October 2027


Auto Skills Center, close to Panzer commissary
• Start: June 2025
• Cost: $9.4 million
• Work: Construct a new auto skills center facility, minimum impact to traffic flow, may cause delays to base access at various stages of construction.
• Estimated completion: October 2027
Housing entrance and basement doors (Buildings 3100–3118)
• Start: May 2026
• Cost: $547,000
• Work: Replace broken entrance and basement doors
• Estimated completion: October 2026
Buildings 2917 and 2918 renovation (close to former high school building)
• Start: August 2025
• Cost: $19.5 million
• Work: Renovate buildings to support DFMWR and administrative functions
• Estimated completion: March 2028
Cobblestone road repair (near Building 2961)
• Start: May 2026
• Cost: $609,000
• Work: Repair Road sub-base and install asphalt pavement, may disrupt traffic flow slightly
• Estimated completion: October 2026
Patch Barracks
Main Access Control Point Closure
• Start: June 2026
• Cost: $1.8 million
• Work: Denial barrier drop arm replacement
• Estimated completion: August 2026
Building 2310 Renovation
• Start: August 2025
• Cost: $19.5 million
• Work: Full interior renovation
• Estimated completion: June 2028
Heating plant repairs (Building 2338)
• Start: March 2026
• Cost: $7.4 million
• Work: Repair office space, flooring and roof
• Estimated completion: June 2027
Temporary access control point (near Swabian Special Events Center)
• Start: March 2026
• Cost: $1.8 million
• Work: Construct a temporary ACP to support main ACP closure for updates
• Estimated completion phase 1 (Road work and Fence Work): June 2026
• Estimated completion phase 2 (overhead structure): December 2026, traffic to be expected
Power Plant II repairs
• Start: March 2026
• Cost: $5.6 million
• Work: Repair facility and install an underground tank
• Estimated completion: September 2027
Child Development Center renovation, phase II (Building 2345)
• Start: February 2025
• Cost: $3.2 million
• Work: Final phase of CDC upgrades
• Estimated completion: August 2026
Family Housing (buildings 2522–2527)
• Start: April 2026
• Cost: $6.8 million
• Work: Full interior renovation of housing units
• Estimated completion: September 2026
Family Housing, Balcony Installation (multiple buildings)
• Buildings: 2400-2405, 2500–2504, 2509, 2511–2515, 2517–2526
• Start: September 2025
• Cost: $4.7 million
• Estimated completion: March 2028


Family housing, install rolladen (multiple buildings)
• Buildings: 2400-2403, 2404-2407, 2411, 2500, 2501, 2504, 2509, 2511-2515, 2518-2530
• Start: December 2024
• Cost: $9.1 million
• Work: Install rolladen window systems
• Estimated completion: May 2028
Kelley Barracks
Child Development Center repairs (Building 3352)
• Start: August 2025
• Cost: $880,000
• Work: Repair water damage and remove mold
• Estimated completion: February 2026
Fitness Center addition
• Start: March 2026
• Cost: $1.8 million
• Work: Addition to existing fitness center, Gym goers can expect minor disruptions in the area as you enter the front door on the left side.
• Estimated completion: To be determined
Robinson Barracks
Robinson Elementary School
• Start: January 2023 (demolition of old buildings)
• Cost: $58.4 million
• Work: Construct a new elementary school
• Estimated completion: May 2028
Family Housing full renovations (Buildings 182 and 183)
• Start: June 2023
• Cost: $15.1 million
• Work: Full interior renovation
• Estimated completion: April 2026
Family Housing Roof Repair (Building 151)
• Start: November 2024
• Cost: $1 million
• Work: Repair existing roof
• Estimated completion: November 2026
Family Housing stairwell painting
• Start: March 2026
• Cost: $573,000
• Work: Paint interior stairwells in multiple housing buildings
• Estimated completion: May 2027
Family Housing renovation (Building 196)
• Start: April 2024
• Cost: $12.8 million
• Work: Full interior renovation
• Estimated completion: April 2026
Family Housing full renovations (Buildings 185 and 186)
• Start: November 2024
• Cost: $13.8 million
• Work: Full interior renovation
• Estimated completion: July 2026
For updates, please follow the Stuttgart Citizen, U. S. Army Stuttgart Facebook page or download the My Army Post App.