Kelley Barracks construction projects update

The construction work about to continue on Kelley Barracks is part of the sewer line upgrades and repairs. Photo by Kevin S. Abel, USAG Stuttgart Public Affairs

USAG Stuttgart Directorate of Public Works

UPDATE, April 30, 2019: Work around buildings 3350 and 3352 begins May 6. The road between the buildings to access parking spaces will be blocked during construction. This work should be completed on May 24. Also, Ash Street will be partially blocked and some parking on Ash and Pine Street (near Bldg. 3315) will be affected due the final asphalt work of the Kelley sewer repair. The CDC drop off, Bldg. 3352 and Bldg. 3368 will be also blocked, but will have a temporarily parking space. The bus stop at Ash Street will not be in service–please use the bus stop at Kelley Hotel, the only pickup stop on Kelley. The work will start on May 11 and should end on May 18. Pedestrians should follow the signs around the working area.

***

UPDATE, March 8, 2019: According to the USAG Stuttgart Directorate of Public Works, Engineering Division, construction work on Ash Street around the Kelley Commissary and Bldg. 3317 continues, with the road and parking spaces blocked beginning March 19

UPDATE, March 1, 2019: 

The  said there will be a partial road and parking space blockage at Ash Street due the sewer repair work.

The work around the Kelley Commissary, and the Post Office and  mail room (buildings 3316 and 3317) will begin on March 13 and should end on April 9 as planned. Pedestrians are asked to follow the signs around the working area. The bus stop near the commissary will be relocated to in front of Bldg. 3318 during the work.

The USAG Stuttgart Directorate of Public Works announces the pedestrian connecting passageway at Bldg. 3320, Kelley Barracks, will be blocked for three days, March 6-8.  The blockage is due to an ongoing construction project. The DPW shops and the parking spaces of Bldg. 3320 won’t be effected during this time; the parking area is always accessible.

The contractor will post signage.

UPDATE Jan. 15, 2019: The contractor performing the sewer line repair work on Ash Street, Kelley Barracks, resumed work today, Jan. 15.  Ash Street will be closed in the area immediately in front of Bldg. 3358.  Access to Kelley Barracks’ main parking lot must be accessed via Maple Street.  

UPDATE, Jan. 7, 2019: Due to the current weather conditions, work on Ash Strasse, Kelley Barracks, has been postponed one week and will resume on Monday,  Jan. 14, weather permitting, instead of Jan. 7. as originally scheduled to resume after the holiday break.

The following are updates to ongoing projects around the garrison.

Kelley Sewer
This project is 70 percent complete. Ash Strasse was open to traffic on Dec. 22 and will remain open until Jan. 6, after which it will close again On Jan. 7.  The work in front of the Child Development Center and buildings 3306 and 3307 area is complete.  The German Kantine parking area has reopened. Currently, the working the area is next to shoppette.  Work required on Oak Strasse in front of flagpole area is tentatively scheduled for February.

Kelley Fitness Center
This project is 90 percent complete. Fire alarm and sprinkler systems were tested Dec. 19. The gym mezzanine and court areas were turned over for use Dec. 20; work continues on the gym interior. Work on restrooms adjacent to court area are scheduled for completion in March.